The Challenge: 
Was to provide a watertight warehouse for the new tenant and also seal in the existing asbestos cement roof sheets with the Chemplas Triskell system, the roof had to be cleaned in line with HSE legislation and the resultant drainage was filtrated by redirecting DWPs through our asbestos filtration units, the rooflights were also at the end of their life expectancy and it was a requirement to replace all the rooflights to ensure a large increase in natural sunlight in this circa 3,600m2 warehouse.

The Solution:

It was always the client’s wishes to have a guaranteed roof on completion but due to the size of the unit the budget was key so it was decided to refurbish  the exsting roof rather than replacement or oversheet, therefore we specified and applied the Chemplas Triskell coating system to the roof following extensive repair work that was necessary to restore the integrity of the substrate, replaced all the rooflights with Brett Martin rooflights and relined the gutters with a plygene gutter liner.

The Results:

The result was the client was left with a 10 year guarantee on the roof on completion with a life expectancy of 15 years for a fraction of the cost of oversheeting or replacement.


Before Video:

Project Description

Location: Units 1-5 Whittle Way, Gatwick Distribution Centre, Crawley, RH10 9RW
Surface Area: 3600m2
Year Completed: 2016
Installer: C & W Industrial Roofing
Contract Administrator: Savills
Products Used: Triskell
Contractor: Paragon Interserve
Value: £200,000